Sunday 23 January 2011

Metropolitan reframe progresses

The reframing of London Metropolitan MD60 continues to make good progress at our Brinwell Road site. A freelance welder/fabricator has been dedicated to the project and has reached the stage where the steel supports that were bracing the upper structure whilst the waistrail was rebuilt have now been removed.

There is still much work to do but MD60 is certainly on the road to recovery. Further horizontal steel sections are required and upon completion, the lower structure steel stress panelling will be welded to the frame structure.